24 Ocak 2017 Salı

Development Life Cycle: Case4-1:Opening Case: of men and mice: a case study

Jackson Laboratory is
  nonprofit,
  independent
  worldreowned
Genetic research institue faunded in 1929.
Located in Bar Harbor,
Budget $80 million,

1200 employee.
Jackson Laboratory decided to install an ERP system with $5 million budget and a 1 year time frame.
Despite the installation challenges, the project's actual cost was close to the budget and took only about 6 months longer than expected.
  Major installation challenge was the integration of its unique mouse-development functions into Oracle's ERP system.
   . One of the problems faced by Jackson stemmed from an internal HR issue (i.e., the risk that the action or inaction of the software provider would hinder the implementation)
   modifying the ERP system to accommodate its business process, placing special emphasis on training, seeking a fixed-fee contract with Oracle and purchasing a surety bond to reduce project risk.


Jackson Lab selected an integrated ERP suite from Oracle rather than a best-of-breed option.
The Oracle applications suite included modules for process manufacturing, accounting, e-procurement, and HR, among others. Their biggest challenge was modification of the Oracle Process Manufacturing (OPM) module to accommodate the lab's unique business processes of raising and distributing mice.
The implementation team chose a phased implementation approach instead of a big-bang approach.
 The first phase initially went live in February, including the management of production capacity, accounts receivable, some general ledger functions, and the purchasing of manufacturing material; in April they launched other modules including accounting for research grants, the rest of general-ledger functions, accounts payable, and fixed assets.
For the second phase, which began in June, the remaining modules including process management, human resources, payroll, labor distribution, and a grant filing application were installed

Jackson faced personnel problems during ERP installation when the best and brightest employees were involved in the implementation process leaving them short-handed to do the everyday work. In addition, Jackson's IT staff lacked experience with ERP, only one person had some experience in installing an ERP. Further cost overruns resulted \ from training, an especially big cost item. The timeand-materials basis contract would have increased the risk of overtime and going over budget because vendors and consultants have an interest in quoting low and seeing the work grow as the project proceeds.
Jackson faced personnel problems during ERP installation when the best and brightest employees were involved in the implementation process leaving them short-handed to do the everyday work. In addition, Jackson's IT staff lacked experience with ERP, only one person had some experience in installing an ERP. Further cost overruns resulted \ from training, an especially big cost item. The timeand-materials basis contract would have increased the risk of overtime and going over budget because vendors and consultants have an interest in quoting low and seeing the work grow as the project proceeds.
There is a natural competitiveness between the buyer and the ERP vendor. vendor benefits by placing a "veil of complexity" over their work; the buyer wants to get the system up and running with the least amount of work and customization.
The service level agreements generay tend to be very complex because much clearer definition of roles and responsibilities between client and service provider is needed. From a consultant's and vendor's perspective, a high (>25 percent) contingency is quite reasonable depending on the nature of the work, whereas this is too much from the buyer's perspective
Jackson Lab used several strategies to reduce the risk. First, they negotiated a fixed-fee contract with Oracle rather than use the more commonly used time-and-l11aterials contract. Second, they bought a surety bond from Gladwyne, a risk management conSUlting firm. This strategy protected Jackson Lab from the project's cost overruns caused by IT staff being forced to solve the technological challenges with "out-of-the-box thinking." Third, it spent considerable time and effort on changing the business processes and training its employees with the new processes. Finally, they got better cooperation from the vendor, Oracle, by negotiating a fixed-fee contract and a favorable service level agreement. In addition, Jackson Lab should have built a time buffer into their ERP implementation life cycle to avoid the pressure of delivering the system on a predetermined timeline. 



Hiç yorum yok:

Yorum Gönder

Kategoriler